1. Manufacturing and assembly of pulverized coal injection system – ICP
Weight: 180 tons of manufacturing of steel structures and boiler, and assembly of 350 tons of structures, boiler and equipment.
Period: from June, 2007 to February, 2008
Location: Juiz de Fora/MG

2. Electromechanical assembly services of the 4th regenerator in partnership with DSI Engineering.
Weight: 450 tons of equipment, structures and pipelines
Period: from January, 2014 to March, 2015
Location: João Monlevade/MG



3. Exchange service of crane track of the steel plant shed
Period: from September, 2014 to November, 2014
Location: João Monlevade/MG